Revised (and original) Milestones
May 15, 1999 - V0 Working Prototype. (April 15)
(May 15, 1999 - D0 robot available for integration testing. This is not a SAM milestone,
but needed for handling MCC99 data and integration tests.)
May 30, 1999 - Integration tests with farm/enstore/sam/d02ka.
May 30, 1999 - Simple Pick Event capability with event database. Tape Import capability (April 30)
June 15,1999 - First Design of Station and Optimizer complete. (May 30)
June 15 1999 - First Design of Interface to Batch System complete. (May 30)
July 15, 1999 - integration with D0 framework and use of SoftRelTools (March 30)
July 15, 1999 - Begin Import Run I data into SAM (no detailed schedule)
July 31, 1999 - V1 Event and File Database.
July 31, 1999 - V0 Implementation of Station, Resource Management and Batch Interface.
Sept. 1, 1999 - Import of MCC99 phase II data as it arrives.
Sept. 15, 1999 - V2 Event and File Database
Sept. 30, 1999 - V1 SAM Servers and Resource Management software complete
Nov. 15, 1999 - V0 design for EDU5(Thumbnail) data access
Dec. 15, 1999 - V2 SAM system including Pick Event and Thumbnail access complete